Which of the following should not be part of the Programme Plan?
  1. Project timescales, costs, outputs, and deliverables
  2. Transition plans
  3. Monitoring and control activities and performance targets
  4. The detailed schedules for every project in the dossier
Explanation
Answer - D - The detailed schedules for every project in the dossier should not be part of the Programme Plan.

Key Takeaway: The Programme Plan will include a list of the projects (the Projects Dossier), their target timescales, and costs, but not their individual detailed schedules.