In which document are project risk escalation routes defined?
  1. Risk Management Strategy
  2. Monitoring and Control Strategy
  3. Benefits Management Strategy
  4. Quality Management Strategy
Explanation
Answer - A - Project risk escalation routes are defined in the Risk Management Strategy.

Key Takeaway: The Risk Management Strategy defines how risks to the programme will be identified, analysed, monitored, and controlled.