Which of the following is NOT one of the three types of programme issues?
  1. A problem or question affecting all or part of the programme in some way
  2. A required change to some aspect of the programme
  3. A previously identified risk that has now hit and requires the appropriate issue management action
  4. A potential change to legislation that may affect the business
Explanation
Answer - D - “A potential change to legislation that may affect the business” is not one of the three types of programme issues.

Key Takeaway: “A potential change to legislation that may affect the business” is a risk not an issue, as it has not yet happened.