M&M’s meat shop decides to conduct a formal requirements ___________. The purpose of this exercise is to verify the accuracy of the requirements
  1. rewrite
  2. restructure
  3. review
  4. release
Explanation
Answer: C - M&M’s meat shop decides to conduct a formal requirements review. The purpose of this exercise is to verify the accuracy of the requirements.

Key Takeaway: A formal requirements review is designed to verify the accuracy of the requirements as well as their clarity. It is also designed to check whether the requirements reflect the business need or problem. Following a review, redundant, vague, incomplete or incorrect requirements will be removed from the document. Furthermore, such a review helps a Business Analyst to judge whether the project is within time and money scope or if it needs modification.