The form identifying deficiencies to be corrected by the contractor is called the __________. This form is normally handled towards the end of the project.
  1. Complaint form
  2. Work order
  3. Punch list
  4. Discrepancy order
Explanation
Answer: C - Punch list
The form identifying deficiencies to be corrected by the contractor is called the punch list