PE Civil Engineering Exam Prep

Category - Civil Engineering

The Concrete Reinforcing Steel Institute (CRSI) recommends that a reinforcing bar (rebar) inspection program be established for all construction projects where reinforcing bars are used. An appropriate checklist for rebar inspection is recommended that includes which of the following items, in addition to those listed below?

- Construction schedule
- Certified mill test and/or bar coating report
- Material shipment schedule
- Potential concerns (possible discrepancies, drawing errors)
- Critical tolerances
- Periodic meeting schedule
  1. Independent testing laboratory reports
  2. Approved placing drawings
  3. A and B
  4. None of the above
Explanation
Answer: C - An appropriate checklist for rebar inspection is recommended that includes independent testing laboratory reports and approved placing drawings in addition to the listed items. CRSI recommends that a checklist procedure and the minimum requirements for rebar acceptance should be established during the pre-construction conference. These quality control measures will help to ensure that the rebar used will meet specific material standards and the project owner’s requirements.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz