PgMP Program Manager Exam Prep

Category - Program Management

Which of the following processes uses Regulations and legislation as an input?
  1. Risk Identification
  2. Quality Planning
  3. Communication Planning
  4. Risk Response Planning and Analysis
Explanation
Answer - B - Regulations and legislation are included in the input to Quality Planning.

Key Takeaway: Quality Planning is a process that identifies which quality standards are relevant to the project at hand and determines how to meet them. The input to the Quality Planning process includes: environment factors, including legislation, product description, and the program scope statement.