PgMP Program Manager Exam Prep

Category - Program Management

Rudy Ninibocker is performing the Close Program process. The outputs of this process would include which of the following?
  1. Final performance review report and program archives
  2. Certificate of program completion and project archives
  3. Lessons learned and contract termination documents
  4. Closure report and contract completion documents
Explanation
Answer - A - The final performance review report and program archives are two of the outputs of the Close Program process.

Key Takeaway: The Close Program process refers to the formal recognition of completion of a program. The outputs of this phase are: a certificate of program completion, the closure report, final performance review, personnel record updates, program archives, and a list of learned lessons from the program review.