Work has begun on a new facility, however the drawings provided by the client are missing a measurement from grade level for the height of the lights to be installed. You should:
  1. Use your best judgement and install the lights regardless.
  2. Halt work entirely until the client can provide the information.
  3. Submit a request for information to the client and continue with other tasks until an answer is provided.
  4. Add the lights to the end of job deficiency list and continue with the project.
Explanation
Answer: C.  Explanation: The client is ultimately responsible to provide accurate information, but the contractor should strive to work as efficiently as possible.