Red Seal Construction Electrician

Category - Construction Electrician

When submitting a job completion package to the client, any approved changes made to the provided drawings should be:
  1. Marked on the drawings in red and stamped to indicate as-built.
  2. Marked on the drawings following the drawing’s formatting as closely as possible.
  3. Provided as a separate document, as changes cannot be made to an engineered drawing.
  4. Marked on the drawings in blue and stamped to indicate as-built.
Explanation
Answer: A.  Explanation: Marking up drawings in red distinguishes the construction changes from any other changes on the drawings.