Which product is an input for the Closing a Project process?
  1. The Project Mandate
  2. The Project Initiation Documentation
  3. The previous Stage Plan
  4. The previous End Stage Report
Explanation
Answer: B - The Project Initiation Documentation.

Key takeaway: When closing a project, it first needs to be evaluated to ensure that all objectives have been met. Since the Project Initiation Documentation is the primary source of information for the project, it is one of the most important inputs to this process. Other inputs include the End of Project Report, the Lessons Log, and the various registers.