Which PRINCE2 theme addresses the ongoing viability of the different project plans?
  1. Quality
  2. Plans
  3. Change
  4. Progress
Explanation
Answer: D - Progress addresses the ongoing viability of the different project plans.

Key takeaway: The Progress theme within PRINCE2 establishes controls that monitor and compare achievements against planned activities. It provides forecasts on project objectives and the continuing viability of the project (in line with the principle of Continued Business Justification), and allows any deviations outside tolerances to be managed and controlled.