Which phase in the program life cycle is closing the program in?
  1. Six
  2. Five
  3. Four
  4. Three
Explanation
Answer - B - Closing the program is in phase five of the program life cycle.

Key Takeaway: Five phases make up a program life cycle: pre-program setup, program setup, establishing program infrastructure, delivering incremental benefits, and closing the program. Closing the program is phase five-the last phase.