Which of the following is true of a Programme Plan?
  1. It is a master project plan.
  2. It is a Gantt chart.
  3. It helps with the detailed management of each project in the programme.
  4. It is a key control document that covers projects and activities.
Explanation
Answer - D - “It is a key control document that covers projects and activities” is true of a Programme Plan.

Key Takeaway: The Programme Plan is used to control and track the progress and delivery of the programme and resulting outcomes.