PMI PMP Project Manager Certification

Category - Project Processes

Which of the following processes are part of the Scope Verification process? Select all that apply:
  1. Update the project management plan
  2. Analyze schedule variances
  3. Verifying the quality of a deliverable
  4. Track and report performance of individual resources
  5. Corrective action
Explanation
Answer: C, E - Corrective action and verifying the quality of a deliverable to meet quality standards are both part of the Scope Verification process.

Track and report performance of individual resources is part of the Manage Project Team process.

Update the project management plan and analyze schedule variances are part of the schedule control process.

Key takeaway: Scope verification tasks overlap with Quality Control processes. Remember that scope verification is all about making sure the deliverables meet the requirements and specifications of the customer.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz