Which of the following are included in the minimum requirements of an Erosion and Sediment Control Plan?
  1. Site drawing of existing and proposed conditions
  2. Narrative discussion of each erosion and sediment control measure, its purpose, construction sequence, and installation timing
  3. Schedule for the inspection and maintenance of temporary and permanent stormwater management, erosion, and sediment control Best Management Practices
  4. All of the above
Explanation
Answer: D - All of the above items are included in the minimum requirements of an Erosion and Sediment Control Plan. The purpose of the plan is to control stormwater runoff from site construction and development that results in soil erosion and sedimentation. Local ordinances require plans for construction site runoff control developed under the U.S. Environmental Protection Agency’s National Pollutant Discharge Elimination System.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz