Which is not a true statement regarding quality?
  1. A project manager should spend a reasonable amount of time on quality management.
  2. A project manager should only check work packages after they are all completed.
  3. A project manager should develop a plan for quality management.
  4. revention should be used instead of inspection.
  5. Gold-plating is not recommended
Explanation
Answer: b - Project managers should be careful to check the quality of all work packages BEFORE they are completed, so they can efficiently initiate a fix if needed. An advanced project manager knows that quality is an integral part of the project and will devote time to creating a plan, and giving others responsibility to help perform quality checks.

Key Take Away: Keep in mind Martin Van Buren’s famous words: “It is easier to do a job right than to explain why you didn't.”