PMI PMP Project Manager Certification

Category - Cost Management

True or false: The lower the better for Schedule Performance Index (SPI) and Cost Performance Index (CPI).
  1. True
  2. False
Explanation
Answer: False. Just remember that when a project’s CPI is below 1.0, then your project is over its budget. If the SPI is below 1.0, then the project is behind schedule.

Key Takeaway: The higher the better for CPI and SPI. This is just a warm-up. We’ll ask you some more questions around this.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz