Supply Chain Management

Category - Dynamics

The key difference between different planning set-ups in this supply chain model is due to _____________ by the supply chain members.
  1. Differences in the decision-making policies
  2. Differences in the Customer Relationship Management
  3. Difference in SRM
  4. None of the above.
Explanation
Answer: A - The key difference between different planning set-ups in this supply chain model is due to differences in the decision-making policies by the supply chain members. Those results affect material orders, production levels, and shipment rates in each phase, and are based on information known to all players in the supply chain.