Interior Design Professional Practice Exam

Category - Interior Design Practice Exam

The design firm notices that a large item on a project has accidently been left off the specifications. The design firm needs to inform bidders of the changes in the contract documents and the contract has not yet been awarded, they should issue:
  1. A change order
  2. An addendum
  3. An alternative specification form
  4. A condition change form
Explanation
Answer: B - an addendum
The design firm needs to inform bidders of the changes in the contract documents and the contract has not yet been awarded, they should issue an addendum.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions