The bank project has run into more expenses on the project than were estimated. What is this called?
  1. Cost performance index
  2. Cost management
  3. Cost forecasting
  4. Cost overrun
Explanation
Answer: D - Cost overrun
The cost overrun is the amount by which actual project cost exceeds estimated cost of a project.