Category - Time Management
A float is determined by the amount of time the activity can be delayed from completion. How much float do Critical Path activities have?
Answer: C - Critical Path activities cannot be delayed, which by definition means that they have a zero float. Key Takeaway: It goes without saying that you need to know what the critical path activities. Remember that based on how things go during the project, slack can be used up and activities that were not on the critical path can be moved on to it.