86. True or false: Retainage is a fee paid is a fixed sum that a client agrees to pay, in advance, to secure the services of a consultant or freelancer.
87. A freak tornado caused damage to a key warehouse during Boris’ vacation in Bora Bora. Boris is concerned over whether his project’s contract covers such a situation. What clause in his Terms and Conditions should John refer to?
88. Handy Dan is working on a highway project. Handy Dan however subcontracts Manny’s Manos to come and pour cement. When the sponsor shows up he doesn’t like the way the cement is being poured and tells Manny’s guys to stop, but they do not. What contractual concept best addresses the above situation?
89. Boris hires an outside vendor to maintain their servers. However, he is extremely concerned about uptime. In order to remain profitable, Boris’ company needs to have 99% uptime. Which of the following would be a clause Boris would want to include in the contract to directly address this requirement?