71. Joe's system has a Recovery Point Objective (RPO) of 24 hours. What does this mean?
  1. Joe's people must be in the office performing the process 24 hours after a disaster or disruption.
  2. Joe has 24 hour to decide what to do in event of an emergency.
  3. No more than 24 hours of data can be lost.
  4. All data related to the process must be recovered within 24 hours.
  5. Joe's process must be restored after 24 hours.
72. The project planning process involves a lot of redundancy, checking and reviewing of plan details; however, to be most effective you shouldn’t publish your proposed project plan until after this important step:
  1. Risk assessment
  2. Segmenting of the WBS into smaller, workable pieces
  3. Receipt of resource commitments
  4. Creation of a budget
  5. None of the above
73. True or false: A risk trigger is what triggers a contingency response.
  1. True
  2. False
74. What is a secondary risk?
  1. A risk that is of secondary importance
  2. Residual risk
  3. Force majeure
  4. Risk that is highly unlikely to occur
  5. Risk caused by another risk response strategy
75. True or false: Both impact and probability can be mitigated.
  1. True
  2. False