21. Based on a real scenario: Hayden the Handyguy wants $50 per hour plus the cost of wood, nails and beer to build some new shelves for Ted the Project Manager who is disappointed what he built fell off the wall. Hayden’s billing method is: (Select the two answers that apply).
  1. Cost plux fixed fee
  2. Time and material
  3. Fixed fee plus percentage of costs
  4. Variable cost
  5. Incentive based fee for performance
22. Which of the following is not recommended as it tends to take the focus off of meeting the client’s intended requirements?
  1. Gold-plating
  2. Just in time
  3. Prevention over inspection
  4. Continuous improvement
  5. PMIS
23. Which set of standards does a project manager typically have the least control over?
  1. Environmental
  2. Organizational
  3. Departamental
  4. Project
  5. Resource
24. A company makes 1,000,000 parts. If fewer than ___ were defective, it would be six sigma quality.
  1. 317,400
  2. 45,400
  3. 2,700
  4. 2
  5. 0
25. What is mutual exclusivity?
  1. If one event occurs, the other cannot
  2. A rule of dating
  3. A measure of variation
  4. A conclusion from a control chart
  5. A conclusion from a scatter diagram