41. Select all that apply - a WBS dictionary can contain which of the following:
  1. Interdependencies
  2. Approval criteria
  3. Detailed description
  4. Numeric identifier
  5. Gold plating
42. When is the project manager using analogous estimating?
  1. The PM doesn’t have all of the information needed to give time estimates
  2. The PM needs to pad their estimates
  3. The PM is using a mathematical model
  4. The PM uses similar projects or activities to assist with time estimates
  5. The PM is using a Monte Carlo technique
43. When is the project manager using parametric estimation?
  1. If the Project Manager is using his instinct to determine the estimated project length
  2. If the Project Manager needs to pad their estimates
  3. If the Project Manager is using Monte Carlo analysis
  4. Using a statistical relationship that exists through historical data or other mathematical relationship
  5. None of the above
44. Which of the following is common problem in project management that is a typical result of unrealistic time estimates by the project manager?
  1. Fast tracking
  2. Critical chain
  3. Schedule compression
  4. Employee changes
  5. Crashing
45. What does the 50/50 rule of progress tracking imply?
  1. An activity is considered 50% complete when it is 50% complete.
  2. An activity is considered 50% complete when it begins and 100% complete when the activity is completed
  3. An activity is consider 50% complete when its successor begins
  4. An activity is credited for 50% complete when it half done, and the other 50% when it is complete