47.Kennedy is utilizing the Precedence Diagramming Method to spec out the first phase of his project at the Tiny Titans Tech Company. This phase of the project involves starting the design for a new website, but he must wait four weeks before he can upload any content. Which method best describes the relationship between these activities?
48.Michael is looking at a network diagram he’s just created for his project. He sits with Tito, a team member and relays important facts about the project utilizing the diagram. Which of the following does not represent the benefits of using a network diagram?