46. What does the 20/80 rule of progress tracking imply?
  1. An activity is considered 20% complete when it is 80% complete.
  2. 80% of an activity is done after the most difficult 20% of an activity is completed
  3. An activity is credited for 20% complete when it half done, and the other 80% when it is complete
  4. An activity is considered 20% complete when it begins and 100% complete when the activity is completed
47. Kennedy is utilizing the Precedence Diagramming Method to spec out the first phase of his project at the Tiny Titans Tech Company. This phase of the project involves starting the design for a new website, but he must wait four weeks before he can upload any content. Which method best describes the relationship between these activities?
  1. Finish-to-start
  2. Start-to-start
  3. Finish-to-finish
  4. Start-to-finish
48. Michael is looking at a network diagram he’s just created for his project. He sits with Tito, a team member and relays important facts about the project utilizing the diagram. Which of the following does not represent the benefits of using a network diagram?
  1. It includes dependences
  2. It illustrates the critical path
  3. t may utilize a calendar scale
  4. It’s a quick sketch
49. True or false: The lower the better for Schedule Performance Index (SPI) and Cost Performance Index (CPI).
  1. True
  2. False
50. The CPI of project is .90, and the EV is $90,000. How much money has actually been spent on the project?
  1. $100,000
  2. $81,000
  3. $810,000
  4. $99,000
  5. $98,100