True or false: The business continuity planner should define the Change Control Process for BCP.

  1. True
  2. False
47.

All of the following are common results of testing and maintaining the business continuity plan except:

  1. Additional funding is added
  2. BCP Project Charter is changed
  3. BCP project plan is changed
  4. Communications management plan is changed
  5. All of the above are true
48. Which of the following are possible stakeholders in business continuity planning choices? Select all that apply.
  1. Police
  2. Local pro sports team
  3. Suppliers
  4. Emergency responders
  5. None of the above