True or false: The business continuity planner should define the Change Control Process for BCP.

  1. True
  2. False
Explanation

Answer: True - According to the Disaster Recovery Institute's Professional Practices, the business continuity planner should define the Change Control Process for BCP.

Key Takeaway: While this may seem like a daunting task, abiding by an organization's established practices for change control in projects is often the best option.