All of the following are common results of testing and maintaining the business continuity plan except:

  1. Additional funding is added
  2. BCP Project Charter is changed
  3. BCP project plan is changed
  4. Communications management plan is changed
  5. All of the above are true
Explanation

Answer. B. The BCP project charter cannot be changed based on risk management planning processes.

Key takeaway: The project charter provides a vision statement for an undertaking and justifies its existence. If you had to change the project charter every time you did a risk assessment, you'd be one frustrated person.