A PERT (Program Evaluation and Review Technique) chart is used to:
  1. Diagram the flow and timing of all activities related to a project
  2. Evaluate employee strengths and weaknesses during performance reviews
  3. Outline responsibilities of staff supervisors
  4. Keep track of vendor compliance with delivery schedules
Explanation
Answer: A - A PERT chart is used to diagram the flow and timing of all activities related to a project. A PERT chart helps to clearly identify key project objectives and to illustrate relationships between tasks.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz