What is the WBS decomposition? Select all that apply:
  1. Breaks down the project into small work packages
  2. A scope verification process
  3. Statement of Work
  4. A key output of the WBS dictionary creation process
  5. A murder board
Explanation
Answer: A - The act of decomposition occurs during the process of creating the WBS, and requires breaking down the project into small work packages.

Key Takeaway: When you finish the decomposition process, you should have work packages that cannot be logically divided into any small pieces, can be manageably estimated and have a tangible outcome.