PMI PMP Project Management

Category - Scope Management

True or false: The WBS is created by the project manager alone.
  1. True
  2. False
Explanation
Answer: False - the WBS is created by the project manager with the team.

Key Takeaway: We want to drive home the point that the WBS is created with the assistance of all the team members who are relevant in the planning process.