Which of these is NOT a feature of the kind of leadership that is required in programme management?
  1. Solves problems and creates novel solutions
  2. Engenders trust with consistent and transparent behaviours
  3. Demands a high level of certainty
  4. Actively engages stakeholders
Explanation
Answer - C - “Demands a high level of certainty” is not a feature of the kind of leadership that is required in programme management.

Key Takeaway: The kind of leadership that is required in programme management required the ability to live with a measure of uncertainty.
Was this helpful? Upvote!
Login to contribute your own answer or details