Which of these would you NOT usually find in a Business Case?
  1. Overall programme schedule showing the relative sequencing of the projects
  2. Investment appraisal
  3. Estimated costs and overall timescales
  4. Cashflow forecast
Explanation
Answer - A - You would not usually find an overall programme schedule showing the relative sequencing of the projects in a Business Case.

Key Takeaway: The programme schedule is included in the Programme Plan.