You have performed a full backup of your server and have developed a rollback plan. Before upgrading this plan in the production environment, what should you do first?
  1. Notify users that the server will be offline.
  2. Test the upgrade plan in a test environment.
  3. Move the resources to another network server.
  4. Document the server’s configuration.
Explanation
Answer - B - Prior to implementing the rollback plan, you should test it in a test environment.

Key Takeaway: It is important to test any updates to be made on a live or production environment in a test environment. Ideally, the live environment should be simulated to the closest match possible. On obtaining satisfactory results, this plan should be implemented in the production environment.