CBAP Business Analyst Exam Prep

Category - Requirements Analysis

What is a secondary risk?
  1. A risk that is not that important
  2. Residual risk
  3. Force majeure
  4. Risk that is highly unlikely to occur
  5. Risk caused by another risk response strategy
Explanation
Answer: E - Secondary risk is a new risk caused by the response to another risk. For instance, ejecting your warp core to avoid a breach may leave you immobile and unable to escape attack. Or for a more realistic example, shifting employees to cover for sick ones may leave you stretched thin in other divisions.

Key Takeaway: Many firms try to avoid paying for protection against risks by believing they can shift resources in the short term. A thorough analysis of the impact of those actions must be conducted.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz