Six Sigma Green Belt Exam Prep

Category - Six Sigma Green Belt

Richard’s Enterprise Resource Planning (ERP) project team members are spending increasingly less time on value-added tasks. As a result, the project’s productivity is declining. What is this an example of?
  1. over-commitment
  2. under-commitment
  3. ERP creep
  4. scope creep
Explanation
Answer: A - Over-commitment to non value-added tasks leads to a productivity decline.
Key Takeaway: A significant challenge for project teams is maintaining a high enough focus on value-added tasks. When team members spend increasingly less time on these tasks, they face a number of problems such as productivity declines. Other problems include delays on delivery and inadequate testing periods.
Was this helpful? Upvote!
Login to contribute your own answer or details