Albert Technologies is developing a new transistor system to launch in 2012. Which Six Sigma project methodology are managers likely to use?
  1. DMADV
  2. DMAIC
  3. DMAIV
  4. DMADC
Explanation
Answer: A - Managers launching a new project are more likely to use DMADV project methodology.
Key Takeaway: Companies that are developing new products and technologies require a Six Sigma methodology that is tailored to the process. DMADV refers to a sequential process of five phases: Define Measure, Analyze, Design, and Verify. Each stage must be implemented successfully before proceeding to the following one.