Group Exercise Instructor Free Test Prep

Category - ACSM Group Exercise Instructor Practice Test

If an activity is judged to be too hazardous to perform, the BEST risk-management approach would be:
  1. Reduction
  2. Retention
  3. Avoidance
  4. Transfer
Explanation
Answer: C - If an activity is judged to be too hazardous to perform, the best risk-management approach would be avoidance. But sometimes it is impossible to completely avoid risk. Two other common ways to reduce risk include ‘reduction” (making changes to the situation or environment to improve safety) and “transfer” (shifting the responsibilities associated with participation from the facility to the participant).