Which is NOT an activity that is part of closing a program?
  1. Shut down the program infrastructure
  2. Disband the program organization
  3. Ensure that all the projects in the program are closed after the program is closed
  4. Perform the transition of program artifacts, benefits monitoring, and ongoing operations to the appropriate groups
Explanation
Answer - C - Ensure that all the projects in the program are closed after the program is closed is not part of closing a program.

Key Takeaway: To ensure safe and smooth program closure, specific activities are performed: review, learn and document, transition, and shutdown. These activities are performed before the actual program is officially closed.