True or false: The WBS is created by the project manager alone.
  1. True
  2. False
Explanation
Answer: False - the WBS is created by the project manager with the team.

Key Takeaway: We want to drive home the point that the WBS is created with the assistance of all the team members who are relevant in the planning process.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz