CompTIA Server+ Exam Prep

Category - Server+

You have performed a full backup of your server and have developed a rollback plan. Before upgrading this plan in the production environment, what should you do first?
  1. Notify users that the server will be offline.
  2. Test the upgrade plan in a test environment.
  3. Move the resources to another network server.
  4. Document the server’s configuration.
Explanation
Answer - B - Prior to implementing the rollback plan, you should test it in a test environment.

Key Takeaway: It is important to test any updates to be made on a live or production environment in a test environment. Ideally, the live environment should be simulated to the closest match possible. On obtaining satisfactory results, this plan should be implemented in the production environment.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz