Category - Time Management

Which tool would be wisest for a project manager to use to present to senior management?
  1. Network analysis
  2. WBS dictionary
  3. Milestone chart
  4. PMIS
  5. Schedule compression chart
Explanation
Answer: C - A milestone chart is an excellent tool to provide updates to senior management. It is simple, clear and provides senior managers with the information they need to know. A network analysis is generally too complicated for a busy senior manager. PMIS stands for project management information system. A PMIS is any software or automated tool for performing project management (for instance, Microsoft Project).

Key Takeaways: A milestone chart emphasizes what has been completed at a high level while providing an overview of what is to come and when it will arrive. This is what senior managers need to manage. Too much information can make it difficult to separate what is important from what is not. They should be able to trust you with the details.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz