Surveying FS

Category - Land Development

Which of the following on-site improvements are developers required to provide when developing a typical subdivision?
  1. Streets, water mains, hydrants
  2. Sewer mains, storm drainage, site grading
  3. Electrical lines, gas lines, fiber optic cables
  4. Answers A and B
Explanation
Answer: D -When developing a typical subdivision, developers are required to provide on-site improvements including streets, water mains, hydrants, sewer mains, storm drainage, and site grading. Privately owned utilities such as electric, gas, and cable typically install their individual utility lines and appurtenances. In certain areas, developers may also be required to provide landscaping, sidewalks, land for open space or other improvements.