When conducting a flush-out, the space can be flushed with large quantities of _________ to remove residual contaminants from construction activities.
  1. Outside air
  2. Conditioned air
  3. Filtered air
  4. Ventilated air
Explanation
Answer - A - When conducting a flush-out, the space can be flushed with large quantities of outside air to remove residual contaminants from construction activities. Outside air shall be used to flush out after construction ends (following issuance of Occupancy Certificate) and prior to occupancy for at least seven days. Two weeks is the recommended ideal length of a flush out.