What term is used for the process whereby a risk within an individual project can be referred to the programme for management?
  1. Sharing
  2. Escalation
  3. Transfer
  4. Absolution
Explanation
Answer - B - Escalation is the term used for the process whereby a risk within an individual project can be referred to the programme for management.

Key Takeaway: Escalation is normally used when a risk to a project is such that it may affect the overall integrity of the programme.