What is the procedure required to achieve LEED certification?
  1. register the project, pay applicable review fees and submit documentation
  2. register the project, retain a LEED professional and pay applicable review fees
  3. pay applicable review fees, submit documentation and submit for appeal review
  4. pay applicable review fees, register the project and submit documentation
Explanation
Answer: A - Projects must first register with GBCI and pay the registration fee. Then, the LEED submittal documentation is compiled and submitted along with the certification fee. Once the review process is completed for both the design and construction credits, a final point tally (and achievement of all prerequisites) dictates the final LEED rating.