True or False: A work authorization system is always required by PMI standards.
  1. True
  2. False
Explanation
Answer: False - A work authorization system is not required. However, it is smart to have in order to keep track and communicate with contractors and employees when to begin executing tasks.

Key Take Away: A work authorization system is often built in at a large company in time-tracking software. Especially on larger, more complex projects where you don’t have a lot of face time with people actually doing the work, this is a good idea. It gives you a chance to ensure previous work was done properly and brief the team execute the new work package on specifics.