Bill is 99.99% sure his system will have 99.99% uptime, well above the 95% requirement agreed upon in the initial project planning. Ted, a senior manager at the firm now believes the system needs to have 98% uptime. True or False: Bill does not need to file a change request.
  1. True
  2. False
Explanation
Answer: False - Bill should file a change request, even if he’s almost certain the additional 3% will never come into play during the life time of the project.

Key Take Away: Over-confidence is a massive folly in project management, but way too common. This is especially the case if you listen to your engineers or programmers, who are always confident in their solutions.